Price raised for continuation of construction of Patrijarha Pavla Blvd – New tender worth EUR 20.5 million published
Source: eKapija
Tuesday, 25.06.2024.
14:27


Ada Bridge (Photo: kokixx/shutterstock.com)

According to the tender that the Belgrade Land Development Public Agency published today, the new price of the job with pertains to Stage 1 of the construction, on the stretch from the Ada Bridge to the section of the boulevard in Rakovica, which is already finished, is RSD 2.4 billion (around EUR 20.5 million).
That is RSD 300 million (around EUR 2.5 million) higher than the price at the previous tender, when it was RSD 2.1 billion (close to EUR 18 million).
Bids were sent whose prices exceed the estimated value of the public procurement - the offer of the group of bidders consisting of Green Decor, Strabag AG and Strabag doo amounted to RSD 2.7 billion without the VAT, whereas the group of companies consisting of ATMBG doo Novi Beograd, D.C. Energocoop d.o.o, Demetra RB doo, DUNEX doo, GEOURBGROUP, Intergradnja COOP d.o.o, RAS inzenjering niskogradnja, RESA gradnja Banovci, SMART FOUNDATION doo and STARTING doo Batajnica offered RSD 2.66 billion, without the VAT, to do the job.
As can be seen, the new price that the Agency set for this job is still below the prices of the only two bidders at the previous tender.
The new tender is open until July 30, and the other details can be found HERE.
Let us remind that the mayor of Belgrade, Aleksandar Sapic, stated earlier that the works, whose value, according to him, was around RSD 2.5 billion, would start as soon as the new contractor was selected and pointed out that it would considerably reduce the problem of the bottleneck occurring on that stretch.
At the beginning of last year, when the second stage of the reconstruction of Patrijarha Pavla Blvd was completed, namely, the section from Kosutnjak to Pere Velimirovica Street, Sapic said that, after the obtaining of the construction permit, a month and a half to two months later, the works on the section from Kosutnjak to the Ada Bridge would begin.
– That means that, if the deadlines are honored, the connecting with the Ada Bridge will be completed in the summer of 2024 – Sapic said at the time and added that the tram infrastructure would also be connected with the Ada Bridge and that there would be two lanes in each direction.
B. P.
Companies:


Green decor d.o.o. Beograd



DEMETRA RB DOO BEOGRAD




SMART FOUNDATION DOO


Tags:
Belgrade Land Development Public Agency
City of Belgrade
Green decor
Strabag AG
Strabag doo
ATMBG doo Novi Beograd
DC Energocoop doo
Demetra RB doo
DUNEX doo
GEOURBGROUP
Intergradnja COOP doo
RAS inženjering niskogradnja
RESA gradnja Banovci
SMART FOUNDATION doo
STARTING doo Batajnica
Aleksandar Šapić
construction of Patrijarha Pavla Blvd
Patrijarha Pavla Blvd
public procurement procedure for continuation of works on Patrijarha Pavla Blvd
Ada Bridge
new tender Patrijarha Pavla Blvd
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.