Tender for water pumping out from Tamnava - Zapadno polje open pit mine underway by July 16



Tender for water pumping out from Tamnava - Zapadno polje open pit mine will be published in the next two day, Milorad Grcic, General Manager of the Mine Basin Kolubara has announced today.
- We are not looking for pumps to rent but water pumping out and mud removal
service – Grcic said at the press conference, adding that the mud quantity in
the open pit mine is still unknown.
After the floods in May in the Tamnava - Zapadno polje open pit mine, there
were 210 milion cube meters of water.
The General Manager of the Mine Basin Kolubara said that whoever applies for a
tender will have to submit an elaborate on water pumping out, drying out and
field estimation after pumping put.
Grcic said that the interested will have 10 days to apply for a tender.
- Deadline for pumping out water from Tamnava defined in the tender will be 105
days – he said.
When asked whether it is enough time to pump out all the water, Grcic said it
is a complex task and that it does not depend only on equipment but weather
conditions as well. Nine dredge machines and a lift machine were flooded in Tamnava.
According to him, they will not wait for 105 days to start the equipment overhaul
but as the water level decreases they will work on it. Grcic said that a dredge
at Tamnava started working but on coal production but on barren soil removal
because, as he added , without removing coal overburden layers, coal production
cannot start.
- Coal production from the Kolubara pit mines in the first half of August
should reach 65.000 tons a day – Grcic said.
On je dodao da je na kopu "Veliki Crljeni" voda skoro ispumpana i da
je nivo oboren za sedam metara.
The General Manager of the Mine Basin Kolubara said that another dredge has
recently been saved and it has already been overhauled. When it starts working,
it will generate 20.000 tons a day.
Grcic said that with these 20.000 tons of coal, total production will reach
targeted 65.000 tons a day which is 75% out of planned coal production in
Kolubara which totals 90.000 tons.
When asked whether there will be sufficient coal for electricity production in
the winter season, Grcic said that the Mine Basin Kolubara already delivers
more coal than anybody expected.