MIHAJLOVIC: Sava Bridge to be Finished in May, Construction of Bypass Route to Bubanj Potok to be Over in Under Two Years
Source: Tanjug
Monday, 27.04.2020.
12:56


Zorana Mihajlovic (Photo: YouTube/screenshot)

Together with the Ambassador of China to Serbia, Chen Bo, she visited the works on the construction of the new Bubanj Potok exchange, which is a part of the section of the Belgrade bypass route between the bridge on the Sava, near Ostruznica, and Bubanj Potok, and which is 20.4 kilometers long.
On this section, whose construction costs EUR 207 million, the main contractor is Power China Construction Corporation, and the subcontractors are Azvirt from Azerbaijan and local companies.
– As for the bypass route, there have been problems with the project-technical documentation and some other unresolved issues regarding the expropriation, but those are all technical things, which we will be able to solve as usual – Mihajlovic said.
With the completion of this section, the 47-km highway from Batajnica to Bubanj Potok will be finished.
Companies:



Tags:
Ministry of Construction
Embassy of China
Power China Construction Corporation
Zorana Mihajlovic
Azvirt
Chen Bo
Bubanj Potok
Ostruznica
Bubanj Potok interchange
Ostruznica bridge
bridge on the Sava
Belgrade bypass route
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.