Construction of gas pipeline through Serbia to be over by the end of the year – Around 1.5 km of pipes laid down each day
Illustration (Photo: Andrea Slatter/shutterstock.com)

This is part of the gas pipeline project between the Bulgarian and the Hungarian border. If everything goes as planned, the works pertaining to the connection to the Russian gas pipeline TurkStream will be completed by the end of the current year, as previously announced.
The workers of the Serbian-Russian company Gastrans are making use of the good weather to complete the final 10 kilometers within the planned deadline.
– This south stream brings security when it comes to gas supply, not just in Serbia, but in all countries it goes through. It is therefore important for Hungary, and probably also for Austria and Germany – said Milos Kravic, the president of the Municipality of Kanjiza.
The construction of the 400-km main gas pipeline should also guarantee energy security for Serbia. The workers say that up to 1,500 meters of pipes are laid down each day. The works began in late April and a large number of local companies are employed on the project.
Tags:
TurkStream
Miloš Kravić
TurkStream gas pipeline
construction of gas pipeline through Serbia
gas supply
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.