Belgrade-Bar route being re-established – Reconstruction of Resnik-Vreoci railway completed
Source: Beta
Monday, 17.07.2017.
13:11


Illustration (Photo: Ivana Vuksa)

The Resnik-Vreoci section is the first phase of the works on the reconstruction of the Resnik-Valjevo railway, 77 kilometers long, which is being realized from the Russian state loan for the modernization of Serbian railways.
The value of the works on the reconstruction of the railway from Resnik to Valjevo amounts to around USD 80 million, and Serbia participates as an investor with 15%, the press release says.
The reconstruction of this section of the railway started on July 7, 2016, and the completion of the section is planned for mid-November 2017.
The modernization and reconstruction of the entire Resnik-Valjevo section will reduce the time needed to travel down the route from 2 hours and 10 minutes to 1 hour and 15 minutes, that is, from 11 to 10 hours from Belgrade to Bar. The completion of the first phase also will reduce the time by half an hour.
The project documentation was prepared by the Institute of Transportation CIP, and the contractor is the Russian company RZD International, along with local subcontractors.
The opening of this section of the railway will be marked at the Main Railway Station in Belgrade.
Companies:




Tags:
RZD International
Belgrade Bar railway
reconstruction of Belgrade Bar railway
Resnik Valjevo railway
Resnik Vreoci railway
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.