Preparations for construction of Welbury Bela Anta, wind park at Dolovo make progress - Deatiled Regulation Plan for 40 wind generators completed


A few years ago, investors from Welbury Bela Anta became interested in the Bela Anta location in Dolovo at Pancevo as a space where winds enable production of electricity through wind generators. Now, the Detailed Regulation Plan of this infrastructure complex done by the designers from the Directorate for the construction of Pancevo has been the subject of public discussion which started October 23.
- The construction of 40 wind generators with up to 3,5 MW was planned and the
total wind filed power cannot exceed 120 MW. This is what the investor wants
and I guess they are conditioned with Elektromreza Srbije. The complex
comprises 93 km of rural roads. It is necessary to change the purpose of the
roads so that the investor could place large wind generators and equipment could
be delivered to the installation place, - Branka Maric, a responsible designer
at the Directorate for construction said for RTV "Pancevo.
Public meeting of the Commission for Plans, where designers will anwer
objections received in the meantime for the Detailed Regulation plan of Bela
Anta will be held December 8. In line
with further procedure, the Assembly of the City of Pancevo should also adopt
the plan so that it would further on be the basis for the project terms for wind
park construction issued by provincial administration.
The space area within the Detailed Regulation plan is 2.167 ha.
For more information on the Detailed Regulation plan of Bela Anta